Obsolescence & Migration · 7 min read · Updated November 2026

PLC and Drive End-of-Life Calendar 2026–2027

A single reference for the discontinuation dates that matter in the next eighteen months — Siemens, Rockwell, Mitsubishi, Omron, Schneider, ABB — with the successor platform and the action we recommend at each date. Verify every line against the manufacturer notice before you buy; notices change.

We maintain this calendar for our own sourcing desk and publish it because customers kept asking for one. Dates come from manufacturer product-change notifications and lifecycle pages as of November 2026; where manufacturers use their own milestone vocabulary we translate it into three plain states: Last order (final date to place an order at list price), Production end (no more new units) and Service end (repairs and spares stop). A line with a date in the past is included because the installed base is still large and the sourcing problem is current.

Siemens

ProductStatusDateSuccessorAction
SIMATIC S7-300 CPUs, ET 200M (6ES7 3xx)Production end (PM410)1 Oct 2025S7-1500, ET 200SPSpares secured; migration plan for critical lines
SIMATIC S7-400 central I/OSpares only1 Oct 2026S7-1500 (ET 200SP HA for process)Audit now; PCS 7 users talk to Siemens about PCS neo path
SIMATIC S7-1200 first generation (G1)Phase-out announced (PM400)1 Nov 2026S7-1200 G2No urgency — long tail; new designs on G2. See G1 vs G2
ET 200SProduction endOct 2023ET 200SPSurplus only; migrate with CPU
Comfort Panels 15 in and larger (1st gen)Phase-out announced1 Oct 2024Comfort Panels V2 / UnifiedStock one spare per critical panel

Rockwell Automation / Allen-Bradley

ProductStatusDateSuccessorAction
PLC-5, SLC 500 (1747/1746)Discontinued / End of lifePastControlLogix 5580 / CompactLogix 5380Migration project; surplus for bridging
MicroLogix 1000/1200/1500DiscontinuedPastMicro850/870Surplus only
MicroLogix 1100/1400End of lifeDiscontinuation announcedMicro870, CompactLogix 5380Last-time buy for spares
1794-ACNR15 FLEX I/O ControlNet adapterEnd of life31 Oct 20261794-AENTR (EtherNet/IP)Replace ControlNet with EtherNet/IP
1734-ADN POINT I/O DeviceNet adapterEnd of life31 Dec 20261734-AENTRSame — DeviceNet is sunset technology
PanelView Standard, PanelView Plus 6DiscontinuedPastPanelView 800, PanelView Plus 7Replace at failure or earlier
1336 PLUS II drivesDiscontinuedPastPowerFlex 525 / 755Replace; note RIO adapters have no successor

Mitsubishi Electric

ProductStatusDateSuccessorAction
MELSEC-F FX3G / FX3GCLast order / production endJun 2026 / Dec 2026FX5U / FX5UC / FX5SSpares for installed base; new designs on FX5
MELSEC-Q Universal CPUs (Q03UDE…Q26UDEH)Last order / production end30 Sep 2026 / 30 Oct 2026MELSEC iQ-R (R04…R120)Urgent spares; migration via RQ extension base
MELSEC-L (listed models)Last order / production end30 Sep 2027 / 29 Oct 2027iQ-R or iQ-FPlan 2027 spares
FX3U / FX3UCProduction end2028FX5UNormal stock still; standardise new machines on FX5
GOT1000DiscontinuedPastGOT2000 / GOT SimpleReplace at failure

Omron

ProductStatusDateSuccessorAction
CJ1G-CPU42P…45P (Europe)DiscontinuedMar 2025NX1P2 / NX102Surplus only
CJ2M-CPU3x (EtherNet/IP)Final order / last shipmentMar 2027 / Jun 2027NX1P2 / NX102Last-time buy for spares in 2026
CJ2M-CPU1x (Europe)Final order / last shipmentJun 2027 / Sep 2027NX1P2Same
CS1, NS-series HMIsWinding downVaries by modelNX7/NJ, NA5Replace HMIs first

Schneider Electric

ProductStatusDateSuccessorAction
Modicon Quantum 140 CPU 434 12U and othersSupport end (varies by reference)8 Oct 2025 to 31 Dec 2030M580 with QEIO adaptersCheck each reference on se.com
Modicon Premium (TSX P57)Discontinued, service onlyStandard service ends 31 Dec 2026 (many references)M580 / M340Migration 2026–2027
Modicon Momentum (170 xxx)End of commercialisationPastModicon STB / X80 distributed I/OFull I/O replacement
Magelis XBT GT / XBT FDiscontinuedPastHarmony ST6 / GTUReplace at failure

ABB

ProductStatusSuccessorAction
ACS550LimitedACS580Replace at failure; stock per ten installed
ACS800Classic / Limited by frameACS880Proactive replacement on critical duty; see the drive guide
ACS350 / ACS355Classic (ACS350) / Active (ACS355)ACS380 / ACS180ACS355 still fine for new machines
AC500 V2 CPUs (PM57x/PM58x)ClassicAC500 V3 (PM56xx)Spares; V3 migration with Automation Builder

How to use this calendar

Match it against your own installed-base list (see the audit method in the S7-300 guide), mark every line where you own the product, and set two dates per line: a last-time-buy date six months before the manufacturer's last-order date, and a migration decision date. The spares formula tells you how many to buy. We update this page when notices change; if you see a date we have missed, tell us.

Reading manufacturer notices correctly

Each manufacturer publishes lifecycle information differently, and misreading it is how plants end up surprised. Siemens uses product-change notifications with PM codes and a "Product Lifecycle" tab on each order number in Industry Online Support; the "Successor" field there is the official replacement and the "spare part availability until" date is the one to put in your plan. Rockwell's Product Lifecycle Status tool shows Active, Active Mature, End of Life (with a discontinuation date) and Discontinued per catalog number, and the "Migration solutions" link gives the mapped replacement. Mitsubishi Electric FA publishes discontinuation notices with a "production discontinuation date" and a "repair acceptance deadline", usually seven years later; the global notice may differ from a regional one, and Japanese-market model suffixes are not always the ones sold in ASEAN. Omron's product discontinuation pages are regional, which is why some CJ2M dates differ between Europe and Asia. Schneider's product pages carry a lifecycle status and an end-of-service date per reference; the Green Premium documents list the substitute. ABB publishes drive lifecycle phases in the Drive Lifecycle Services guide with the Classic and Limited phase dates per frame size.

Building your own tracker

Keep a spreadsheet with one row per order number you own: quantity installed, quantity in stock, manufacturer lifecycle state and date, successor, migration decision date, owner. Review it quarterly against the manufacturer sources; the whole review takes an hour once the list exists. Subscribe to the manufacturers' lifecycle notification services (Siemens "Product notes" subscription, Rockwell Knowledgebase notifications, Mitsubishi FA news) so changes arrive by email. For plants with several hundred order numbers we run this review as a service and return the updated sheet with sourcing options for every line that changed state.

Need engineering help with this?

Our engineers apply this to real projects every week — selection, specification, commissioning. Send your question or a part number.

Request a quote Talk to an engineer

Quick answers

Where do these dates come from?

Manufacturer product-change notifications and lifecycle portals (Siemens Industry Online Support, Rockwell Product Lifecycle Status, Mitsubishi Electric FA discontinuation notices, Omron and Schneider product pages), as read in November 2026. Always confirm the exact part number against the current notice.

What is the difference between "last order" and "production end"?

Last order is the final date to place a purchase order with the manufacturer at normal conditions; production end is when the last units are built. After production end only distributor stock and surplus remain, and prices move with scarcity.

Can you source parts after the production end date?

Usually yes, from distributor residual stock, manufacturer spare-part programmes and tested surplus. We record firmware, series and origin for every unit and state them in the quotation.